Construction Progress

OCTOBER 2020 LOOK AHEAD

  • Complete exterior framing and Sheathing.
  • Complete storm and vent piping to the roof.
  • Install roof blocking and roof curbs.
  • Start roofing installation by the end of the month.
  • Start duct work and water piping above ceiling.
  • Install brick ties and flashing on exterior walls.
  • Start air barrier and spray foam installation at exterior walls by the end of the month.


October 2, 2020: What a difference a few months can make!

SEPTEMBER PROGRESS

  • Remaining floor slab poured.
  • Mobilized and installed all Structural Steel/Joist and roof decking. Including Inspections.
  • Completed install of gas line extension for the new addition.
  • Replaced the schools main breaker for added power needed for the addition.
  • Performed interior and exterior wall layout.
  • Started exterior wall framing.
  • Started above ceiling storm and vent piping to the roof.
  • Poured steel column bases, locker bases, and equipment housekeeping pads.


Exterior framing


Interior concrete infill


Steel installation

SEPTEMBER 2020 LOOK AHEAD

  • Main level slab pour on 9/4/20.
  • Mobilize crane and steel. Start steel erection week of 9/7/20.
  • Complete Install of new gas service for the addition.
  • Start exterior wall framing/sheathing before the end of the month.


September 4, 2020: Main level slab pour.

AUGUST 2020 PROGRESS

  • Site storm piping structures and tie ins completed.
  • Electrical feeds and Sprinkler Main installed in the existing bldg. to the addition complete.
  • Plumbing and Electrical below slab installs completed.
  • Prep and poured lower floor slab.
  • Prep complete at main level floor slab for pour scheduled for the week of 9/1/20


 Setting forms and preparing for concrete in the lower section of the addition.


Plumbers have roughed in plumbing for the new science rooms.


Concrete is pumped into the lower section of the addition.


Masons finished the separation firewall between the addition and the existing building.

JULY PROGRESS


Aerial photo showing the progress made so far. The foundation work will continue over the next few weeks.

PRE-CONSTRUCTION

Aerial photo showing the location for the new addition prior to construction beginning this summer.